Hood Aerodrome Project
18 July 2024
Runway
The sealed runway 06/24 is now open.
The back-up plan was implemented to ensure the aerodrome was operational for the winter (we didn’t want to rely on the grass runway over this time). This involved placing a temporary seal over the extended sides of the runway and apron to protect it during the cold weather.
The work will recommence in November and will take approximately four weeks for asphalting and painting.
Lighting
The design is underway and is due to be complete in August. The Council will then go to market to procure the solution. Once a contract is in place, the installation timeline will be confirmed.
Services
The design of services (water, wastewater, power) and internal roading and taxiways to support future hangar development is underway and is due to be completed by the end of August. Consenting the design and procuring a contractor will take place over September and October. Once a contract is in place, the construction timeline will be confirmed.